During 2023, the Prada Group started a series of implementations aimed at improving the optimization of energy consumption, with the construction of new photovoltaic systems.
More in detail:
- The construction of the first photovoltaic plant at the Milan headquarters at 28 Via Fogazzaro;
- Following the completion of the Levanella Logistics Hub (AR), the FTV plant on Building 3 was completed, which, via an underground power line, transfers the energy produced to the adjacent space (old Hub);
- For the Buresta (AR) and Figline (FI) factories, two new plants were completed on existing buildings;
- At the footwear plant in Montegranaro (FM), the structure of the present plant was expanded;
- The industrial site in Torgiano (PG) saw not only the construction of a new photovoltaic plant but also the completion of the last building.
This resulted in an increase in power of 1,412.76 KWp in 2023, compared to 2022, for a total of 4,966.321 KWp.